Does anyone know if during the move to 36tph in WTT37 (or later, is the resolution of the timetable to remain at 15 second intervals, or will it change to 10 second intervals. I would have thought that to run a 36tph/100sec headway service the latter would be more sensible?
|
|
|
WTT37
Jan 24, 2015 12:17:00 GMT
Post by seaeagle on Jan 24, 2015 12:17:00 GMT
Still staying at 15 seconds for the time being.
|
|
|
WTT37
Jan 24, 2015 12:27:49 GMT
Post by superteacher on Jan 24, 2015 12:27:49 GMT
When is WTT 37 due?
|
|
|
WTT37
Jan 26, 2015 16:06:12 GMT
Post by Dstock7080 on Jan 26, 2015 16:06:12 GMT
WTT37 due Sun 8 March. Uplift to 36tph peak (27tph off-peak) not due until WTT39 due April 2016, preparations include a 23 day blockade in August 2015 to support track works at Walthamstow Central.
|
|
|
WTT37
Jan 26, 2015 17:13:00 GMT
Post by will on Jan 26, 2015 17:13:00 GMT
So if 36tph is to be introduced with WTT39 in April 2016 what will be different in WTT37?
what track work is required at Wathamstow, will anything major have to be done to turn around 36tph there more so than Brixton. Thanks
|
|
|
WTT37
Jan 26, 2015 18:06:55 GMT
will likes this
Post by Dstock7080 on Jan 26, 2015 18:06:55 GMT
WTT37 "Maximising benefits of upgrade, Further off-peak enhancement to 26.6tph There will be a 23-day blockade in August 2015 to support track works at Walthamstow Central and a 52-hour closure to the line in early 2016 to carry out works to Northumberland Park Depot which will result in trains being able to get into service more quickly".
No details more at this stage.
|
|
North End
Beneath Newington Causeway
Posts: 1,769
|
WTT37
Jan 26, 2015 20:21:32 GMT
Post by North End on Jan 26, 2015 20:21:32 GMT
So if 36tph is to be introduced with WTT39 in April 2016 what will be different in WTT37?
what track work is required at Wathamstow, will anything major have to be done to turn around 36tph there more so than Brixton. Thanks The work at Walthamstow would be replacement of the scissors crossover. The need to replace this crossover has been a headache for some time, such that it has been put off as far as possible. If I recall correctly it has had a 'temporary' speed restriction on it for many years now. A faster run in/run out would enable an increase in service. I know an aspiration for the Victoria Line is for as many trains as possible to run through to Walthamstow. Good news for Walthamstow, but it will upset a few from the likes of Finsbury Park who know that they stand much more chance of a seat if they wait for a Seven Sisters starter!
|
|
|
WTT37
Jan 27, 2015 10:03:24 GMT
Post by snoggle on Jan 27, 2015 10:03:24 GMT
WTT37 due around 26 April. Uplift to 36tph peak (27tph off-peak) not due until WTT39 due April 2016, preparations include a 23 day blockade in August 2015 to support track works at Walthamstow Central. Interesting. IIRC the proposal to blockade Walthamstow was supposed to have been done a couple of years ago but then disappeared from the engineering works look ahead. It's going to be some operation to replace the northern section for 23 days with some form of bus service. I assume TfL will also try to maximise capacity on what will be the Overground service into Liverpool Street to offer some form of alternative service.
|
|
Deleted
Deleted Member
Posts: 0
|
WTT37
Jan 30, 2015 20:37:57 GMT
Post by Deleted on Jan 30, 2015 20:37:57 GMT
It should be noted that under the old-signalling/trains, and before the speed restriction came into effect, that the Walthamstow crossover had an approx. 6 second faster platform re-occupatiin time compared to Brixton (90s vs 96s).
|
|
|
WTT37
Feb 17, 2015 19:22:33 GMT
Post by snoggle on Feb 17, 2015 19:22:33 GMT
TfL have now released a press release about the blockade at Walthamstow. Sets out some of the details of the replacement bus services which look to be very comprehensive and stretching far and wide.
|
|
Antje
侵略! S系, でゲソ! The Tube comes from the bottom of London!
Posts: 603
|
WTT37
Feb 17, 2015 21:18:39 GMT
Post by Antje on Feb 17, 2015 21:18:39 GMT
What makes it difficult for the current Walthamstow crossover to attain 36 tph? Is it because of the age or the crossover needs to be longer?
|
|
|
WTT37
Feb 18, 2015 0:34:27 GMT
via mobile
Post by londonstuff on Feb 18, 2015 0:34:27 GMT
|
|
Tom
Administrator
Signalfel?
Posts: 4,083
|
WTT37
Feb 18, 2015 23:27:45 GMT
Post by Tom on Feb 18, 2015 23:27:45 GMT
What makes it difficult for the current Walthamstow crossover to attain 36 tph? Is it because of the age or the crossover needs to be longer? Both, really. Itäs a combination of Geometry and Condition, and as North End says there has been a speed restriction over it for some years now.
|
|